Overview

Transportation Program Overview

By 2042, the Treasure Island neighborhood will grow by up to 8,000 homes—many offered at below-market rates—housing more than 20,000 new residents. Along with more housing, this new development includes extensive open space, hotels, restaurants, shops, and entertainment venues.

This new activity will result in tens of thousands of additional trips to and from the island each day. The Treasure Island Mobility Management Agency is developing a comprehensive transportation program that will meet the current and future needs of residents, workers and visitors to ensure a vibrant community.

The Treasure Island Transportation Program is governed by the San Francisco Board of Supervisors in its capacity as the Treasure Island Mobility Management Agency Board. 

Transportation Program Goals

The Treasure Island Transportation Program is guided by two performance goals: that at least 50% of trips are made by walking, biking, and taking transit, and that the program be financially self-sufficient. We can achieve this by:

Promoting walking and biking: Bike lanes, pedestrian paths, and Lyft Bike bike sharing will make biking and walking around the island safe and enjoyable.

Providing high-quality transit: More Muni service, along with new AC Transit, ferry service, and an on-island shuttle will help ensure that at least 50 percent of trips to and from the island are made using sustainable modes.

Reducing the need for car ownership and use: People who drive will pay a toll for driving on and off of the island. The cost of housing will not include parking, so people who own cars will pay for parking separately. Access to car share vehicles will make it easier to live without owning a personal vehicle on the island.

Promoting affordability: Subsidized transit passes and discounts to services like car and bike share will make transit affordable and accessible to longtime residents and people living in below market-rate housing. 

Achieving financial sustainability: The transportation program should be financially self-sustaining when 4,500 of the 8,000 housing units have been occupied.

Estimated Timeline (subject to funding)

This timeline shows key milestones in Treasure Island's redevelopment. The Treasure Island Mobility Management Agency is working to secure funding to implement the transportation improvements.

Image
Timeline graphic (decorative)
  • Implementation Milestone
  • Transit Milestone
  • Residential Milestone

2006

First Transportation Plan developed, including toll

2008

State legislation authorized Treasure Island toll

2011

Treasure Island Development Agreement executed

2016

TIMMA Board approved initial toll policies

Fall 2019

Macalla Road construction began  1

Toll exemption for existing residents adopted

Summer 2020

Southgate Road Realignment construction began  2

2022

Interim Ferry Service started  6

Residents began moving into new housing

2023

Southgate eastbound off-ramp opened  2

West Side Bridges construction began  3

2026

West Side Bridges completed  3

Hillcrest Road construction completed  4

Bikeshare launches

Treasure Island Roadway Improvement Project started  5

2027

Permanent Ferry service begins (pending funding)  6

On-island shuttle service begins (pending funding)  7

2028

Quarter buildout of Treasure Island housing (2,000 units)

Macalla Road final configuration completed  1

Treasure Island Roadway Improvement Project completed  5

East Bay service begins (pending funding)  8

Initial increases in Muni bus service  9

2033

Half buildout of Treasure Island housing (4,000 units)

Further increases in Muni bus service; ramp-up complete  9

2042

Full buildout of Treasure Island housing (8,000 units)

Timing TBD

Tolling begins

Transit pass program rollout

Image
A map of Treasure Island Implementation Milestones, with numbered dots identifying the following projects: (1) Macalla Road; (2) Southgate Road Realignment; (3) West Side Bridges; (4) Hillcrest Road; and (5) Treasure Island Roadway Improvement Project.
Image
A map of Treasure Island Transit Milestones, with numbered dots identifying the following projects: (6) Ferry Service; (7) On-Island Shuttle Service; (8) East Bay Bus Service; and (9) Increased Muni Bus Service.

Program Partners

  • Treasure Island Development Authority
  • San Francisco Municipal Transportation Agency
  • San Francisco Bay Ferry
  • AC Transit
  • Metropolitan Transportation Commission
  • Caltrans

Resources

Treasure Island Development Authority website

Contact 

Suany Chough, Assistant Deputy Director for Planning

Key Features
A map showing future transportation improvements on Treasure Island and Yerba Buena Island, including walking and biking paths throughout the islands, a shuttle on Treasure Island, ferry service to Downtown San Francisco from a new terminal on Treasure Island, new bus service between the new ferry terminal and Downtown Oakland, new bus service between the new ferry terminal and San Francisco Civic Center, and improved bus service between the new ferry terminal and the Salesforce Transit Center.

Use this form for any questions or comments you have about the Treasure Island Transportation Program, including the toll and affordability program, transit services, transit passes or parking policy. (Be sure to include your email address if you'd like a response to your question.)

Transportation Programs Under Development

Bus, Ferry, Walking, Biking, Shuttle 

We are working to deliver the following public transit services. The implementation of these services is still pending funding.

  • New ferry service between Treasure Island and San Francisco: A new ferry service between Treasure Island and the San Francisco Ferry Building will operate seven days/week (hours and frequency to be determined, pending funding). SF Bay Ferry will operate this service with a new electric vessel. Visit our ferry service page for more information.
  • Bike share: Lyft Bike bike sharing is now available for residents, visitors and workers on both Treasure Island and Yerba Buena Island. Visit our bike share service page for more information. 
  • On-island passenger shuttle: An on-island shuttle will provide a “last-mile” connection for transit riders. The shuttle will serve Treasure Island and Yerba Buena Island, connecting residential buildings, parks and other destinations, and transit services.  Initially, this shuttle service may be combined with East Bay service to serve lower demand levels more cost-effectively.
  • Future East Bay bus service: A new direct bus service will connect Treasure Island to Oakland Civic Center. During the initial years of the program, the East Bay route will likely operate as an on-demand service.
  • Car share and programs like carpool matching: A carshare provider will offer their services on-island. Carshare members will have the ability to check out vehicles for use, making payments based on the total duration of the check-out period and/or the distance driven.
  • Walking paths and pedestrian-only streets: Pedestrian/bike paths are being constructed with general development of the Islands. A multi-use path for bicyclists and pedestrians connecting Vista Point on Yerba Buena Island to the Treasure Island ferry terminal will be constructed as funding is secured.

Transit Passes 

As part of the Treasure Island Transportation Program, a Treasure Island transit pass will be available on Clipper, providing unlimited rides on all Muni, AC Transit, and the Treasure Island ferry. Treasure Island residents in below-market rate housing will qualify to purchase this pass at a 50 percent discount. Treasure Island residents in market-rate housing will be required to purchase this same monthly Treasure Island transit pass at regular price. This pass is still under development.

Parking

The SFMTA Board adopted on-street parking legislation for Treasure Island in 2026. Parking meters and signage will be installed on newly constructed public streets. 

For residents of Treasure Island, parking spaces will be purchased or leased separately from the cost of housing.

Toll and Affordability Program 

The toll and affordability program is under development. The toll will help manage congestion and revenues will support expanded transit service and other transportation improvements. Visit our Toll and Affordability Program page for more information. 

Public Engagement
Project staff taking feedback from residents at an open house on January 20, 2024.

Treasure Island residents attend an Open House at the Ship Shape Community Center on January 20, 2024.

The Transportation Authority is working closely with Treasure Island residents, businesses, community organizations, housing providers, island developers, and the Treasure Island Development Authority on the transportation program. 

Use this form for any questions or comments you have about the Treasure Island toll, transit, transit passes or parking policy. (Be sure to leave an email if you'd like a response to your question.)

Past Events

May 13, 2026 Treasure Island Development Authority Board

Treasure Island Development Authority Board Presentation (PDF)

June 11, 2024 Treasure Island Mobility Management Agency Committee

Download the June 11, 2024 Presentation (PDF)

January 20, 2024 Treasure Island Community Open House

We participated in a community open house hosted by District 6 Supervisor Dorsey, in cooperation with Treasure Island Development Authority, One Treasure Island, Treasure Island Development Group, and a collaboration of City agencies to share information about neighborhood development, transportation updates, and how we are working together to meet the needs of the people that live here today.

July 28, 2022 Public Outreach

Download the July 28, 2022 outreach presentation (PDF)

Download the July 28, 2022 outreach handout (PDF)

November 17, 2021 Public Outreach

Download the November 17, 2021 Public Outreach presentation (PDF)

September 14, 2021 Treasure Island Outreach for Businesses and Workers

Download the September 14, 2021 presentation (PDF)

Click here to send us comments or questions about the September 14, 2021 recorded event

April 3, 2021 Treasure Island Community Meeting

Program updates to Board

Download the June 2021 Toll Affordability Program update presentation to TIMMA Committee (PDF)

Download the January 2020 Program Development and Ferry Service planning update presentation (PDF)

Reports & Documents

2022

Treasure Island Mobility Management Program Implementation Report DRAFT (PDF)

Report provides updates to the 2011 Treasure Island Transportation Implementation Plan. Report lays out a transportation program with a series of measures and strategies that will meet the transportation goals of the Redevelopment of former Naval Station Treasure Island.

2021

Approval of toll affordability program for businesses and workers (PDF)

2019

Approval of a toll exemption for current residents of Treasure Island (PDF)

Treasure Island Demand Model Analysis Report For years 2025, 2030, and 2035 (PDF)

Report summarizes results from the 2019 Treasure Island travel demand model for years 2025, 2030, and 2035.

2016

Treasure Island Mobility Management Agency Board Resolution No. 17-03 (PDF)

Resolution approving the Treasure Island Mobility Management Study Toll Policy Recommendations. Includes the Treasure Island Mobility Management Study itself, as well as a memo to the Treasure Island Mobility Management Committee recommending approval.

Treasure Island Mobility Management Study Summary Report (PDF)

A preliminary set of recommendations for the congestion toll aspect of the Treasure Island Mobility Management Program.

2015

Treasure Island Transportation Survey Final Report (PDF)

Overview of key findings from the fall 2014 Treasure Island Transportation Survey.

2014

Economic Development Conveyance Memorandum of Agreement between the Treasure Island Development Agency and US Navy

Establishes the terms, conditions, and schedule governing the transfer of title of the former Naval Station Treasure Island property excluding property to be retained by the U.S. Coast Guard and the U.S. Jobs Corp to TIDA.

Treasure Island Mobility Management Agency Board Resolution No. 110-14 (PDF)

Resolution designating the San Francisco County Transportation Authority as the Treasure Island Mobility Management Agency for certain purposes pursuant to the Treasure Island Transportation Management Act.

2012

Transportation Authority Board Resolution 12-16 (PDF)

Resolution recommending that the Treasure Island Development Authority and San Francisco Board of Supervisors designate the Transportation Authority as the Treasure Island Mobility Management Agency to implement the Treasure Island Transportation Program.

2011

Treasure Island Transportation Implementation Plan (PDF)

Formative plan that identifies key principles, policies, and strategies for the Treasure Island/Yerba Buena Island Transportation Program.

Treasure Island Design for Development

The Design for Development describes the overarching vision, as well as specific design standards and guidelines, that will guide development. The Design for Development implements the Treasure Island/Yerba Buena Island Special Use District of the San Francisco Planning Code. Approved by the Board of Supervisors.

Disposition and Development Agreement

Approved in 2011, the Disposition and Development Agreement governs the developer's ability to develop the project through a series of Major Phases and Sub-phases, as well as the developer's obligations with respect to project elements including public infrastructure, affordable housing, and community benefits.

Final Environmental Impact Report 

The Final Environmental Impact Report provides an overview of the environmental impacts related to redevelopment of Treasure Island, as well as the proposed methods for mitigation of these impacts.

Treasure Island/Yerba Buena Island Project: Economic Impact Report (PDF)

The report was prepared by the Office of the Controller. 

2008

California Assembly Bill 981

Authorizes pricing program by enacting the Treasure Island Transportation Management Act. Calls for a Treasure Island Mobility Management Agency to manage implementation and operations of the Treasure Island Transportation Implementation Plan for the transportation program on Treasure Island and Yerba Buena Island.

Related Work

Image

Treasure Island and Yerba Buena Island are now part of the Lyft Bike system! With over 300 stations and 4,500 bikes already in San Francisco, Lyft Bikes will expand with seven new stations on TI and YBI this fall.
Image

Ferry service is available between Treasure Island and the San Francisco Ferry Building.
Image

Muni’s 25 Treasure Island line serves Treasure Island from the Salesforce Transit Center.
Image

The toll and affordability program is under development. The toll will help manage congestion and help pay for expanded transit service and other transportation improvements.